What is the total cost of reducing the project to 18 weeks? 11eab92b_c478_9370_99e6_ff29173699cf

Correct Answer

verifed

verified

Total cost...

View Answer

In crashing this project,which activity is the first to be reduced 11eab92b_c478_6c5c_99e6_8ba485fd2ad1

Correct Answer

verifed

verified

A costs $8,000,D cos...

View Answer

The latest starting time for an activity is equal to the latest finish time minus the activity time.

Correct Answer

verifed

verified

Which of the following is not an advantages of CPM/PERT?


A) Relationships among activities can be identified.
B) Activities that need to be watched closely can be identified.
C) Arrows and nodes depict sequential relationships.
D) Slippage in project activities is no longer an issue
E) Paths are clearly identified.

Correct Answer

verifed

verified

Scope creep refers to the tendency for projects to take longer than planned.

Correct Answer

verifed

verified

The earliest finish time for an activity is equal to the latest finish time minus the activity time.

Correct Answer

verifed

verified

The owner of Ace Building Co.is about to begin work on a project comprised of the following four activities: The owner of Ace Building Co.is about to begin work on a project comprised of the following four activities:   What is the estimated expected (mean) duration for project completion? A) 41 days B) 70 days C) 100 days D) 120 days E) 221 days What is the estimated expected (mean) duration for project completion?


A) 41 days
B) 70 days
C) 100 days
D) 120 days
E) 221 days

Correct Answer

verifed

verified

Which of the following is used to compute the earliest finish times once the earliest start times are calculated for an activity on a precedence network?


A) Expected activity duration
B) Activity slack time
C) Activities that are on the critical path
D) Variance in project duration
E) Maximum project duration

Correct Answer

verifed

verified

What is the critical path for this project network? 11eab92b_c478_4547_99e6_511656fcc313

Correct Answer

verifed

verified

A project manager for Durable Construction Co.is about to build a house involving the following six activities: A project manager for Durable Construction Co.is about to build a house involving the following six activities:   What is the estimated standard deviation of the duration for activity E? A) 1 day B) 2 days C) 3 days D) 4 days E) 5 days What is the estimated standard deviation of the duration for activity E?


A) 1 day
B) 2 days
C) 3 days
D) 4 days
E) 5 days

Correct Answer

verifed

verified

In "crashing",a project manager will generally focus on activities which:


A) are not on the critical path.
B) are the least costly to crash.
C) are costly to crash and are on the critical path.
D) are on the critical path and are the least costly to crash.
E) have the most slack

Correct Answer

verifed

verified

Uncontrolled changes to a project is called:


A) cost creep
B) project randomness
C) scope creep
D) transferring risk
E) avoidance

Correct Answer

verifed

verified

For the PERT/CPM technique,completing the backward pass includes making the latest finish (LF)equal to the earliest finish (EF)for the end activity.

Correct Answer

verifed

verified

The manager of a National Forest is about to undertake a reforestation project in a burned out area.The project will involve the following six activities: The manager of a National Forest is about to undertake a reforestation project in a burned out area.The project will involve the following six activities:   What is the estimated slack time for the path U-W-Z? A) 0 days B) 25 days C) 35 days D) 45 days E) 85 days What is the estimated slack time for the path U-W-Z?


A) 0 days
B) 25 days
C) 35 days
D) 45 days
E) 85 days

Correct Answer

verifed

verified

Determine the amount of slack in each of a project's activities (see the list below),and identify those which are on the critical path. 11eab92b_c477_d00c_99e6_b5da5d6cfdf6

Correct Answer

verifed

verified

Deterministic networks use three duration estimates for each activity in order to best determine the activity's estimated duration.

Correct Answer

verifed

verified

Within what amount of time (in weeks)is there a 90% probability that the critical path for this project will be completed? 95%? 99%? 11eab92b_c478_6c5a_99e6_a9bae40ac5bd

Correct Answer

verifed

verified

There are four activities on the critical path.Coincidentally,the standard deviations for their durations are all equal to 4.The standard deviation of the duration for the critical path is therefore equal to:


A) 2
B) 4
C) 8
D) 16
E) 64

Correct Answer

verifed

verified

The principal advantage a Gantt chart has over other project scheduling techniques is:


A) its ability to reveal relationships among activities.
B) it illustrates multiple paths as a project network.
C) it focuses on the critical path.
D) its simplicity.
E) both cost and time are included in the chart.

Correct Answer

verifed

verified

What activities make up the critical path? 11eab92b_c478_6c5b_99e6_a72e7a6faa52

Correct Answer

verifed

verified

Critical p...