How does the HPE c7000 BladeSystems use of network infrastructure compare with the HPE Apollo 6000's?


A) The HPE c7000 BladeSystem offers less port variety.
B) The HPE c7000 BladeSystem offers greater port consolidation.
C) The HPE Apollo 6000 offers greater per server connectivity.
D) The HPE Apollo 6000 uses fewer network ports per server.

Correct Answer

verifed

verified

An architect needs to determine whether a customer is ready to move to a software-defined data center (SDDC) . Which additional information should the architect obtain from the customer to verify this?


A) whether they have a disaster recovery plan implemented
B) whether they have a workplace mobility plan implemented
C) whether they have a management and automation solution implemented
D) whether they have standardized on a single vendor

Correct Answer

verifed

verified

A customer plans to migrate from two fully depreciated high end Relational Database Management System (RDMS) servers, which are out of warranty and still under a support contract. An architect has recommended the customer migrate to four new HPE Superdome X BL920 (2P/18C) blades running Microsoft SQL server. Which cost statement provides a rationale for the migration?


A) Based on the TCO/ROI analysis for this project, the Apollo 4510 System makes a better choice as a SQL Database server platform for this migration
B) The amount of savings from not renewing the service contract on the existing equipment can pay for the new hardware in just a little over three years
C) The NPV of -$100,000 USD more than justifies the purchase price of the new equipment
D) The IRR for this proposal would have to be extended out for ten years to make sense, as the IRR value for the first three years is nearly 20 percent

Correct Answer

verifed

verified

A customer is planning to migrate from a Virtual Connect Enterprise Manager (VCEM) environment to HPE OneView. Which topic should the architect discuss with the customer before the migration is implemented?


A) that HPE OneView Advanced licenses should be added to the appliance prior to the migration
B) that direct migration from the VCEM is not possible and the customer should plan to remove VC Domain from VCEM first
C) that migration to the HPE OneView will replace existing WWNs and MAC addresses with new ones, assigned by HPE OneView
D) that additional one-time-use licenses are required for migration

Correct Answer

verifed

verified

View the Exhibit. View the Exhibit.     Refer to the exhibit. An architect is planning an HPE Moonshot System with m710 cartridges to support a customer application virtualization solution. The customer indicated that the maximum acceptable response time for the solution is three seconds. The architect has implemented a POC and tested a single cartridge with different numbers of user sessions. The architect monitored resource utilization throughout the tests. The results of the test with the point at which the response time exceeded three seconds are shown, marked as the  VSI max.  What should the architect conclude from this test? A)  CPU becomes a limiting factor around 50 sessions, so the architect should propose at least one cartridge per 45 or 50 users. B)  None of the monitored resources shows signs of being a bottleneck, so the architect should consider other factors such as the HPE Moonshot switch module. C)  The network adapter becomes a bottleneck before other resources, so the architect should propose m710p cartridges, which provide 10GbE ports. D)  The memory becomes a bottleneck before other resources, so the architect should propose m400 cartridges, which provide a higher memory capacity. View the Exhibit.     Refer to the exhibit. An architect is planning an HPE Moonshot System with m710 cartridges to support a customer application virtualization solution. The customer indicated that the maximum acceptable response time for the solution is three seconds. The architect has implemented a POC and tested a single cartridge with different numbers of user sessions. The architect monitored resource utilization throughout the tests. The results of the test with the point at which the response time exceeded three seconds are shown, marked as the  VSI max.  What should the architect conclude from this test? A)  CPU becomes a limiting factor around 50 sessions, so the architect should propose at least one cartridge per 45 or 50 users. B)  None of the monitored resources shows signs of being a bottleneck, so the architect should consider other factors such as the HPE Moonshot switch module. C)  The network adapter becomes a bottleneck before other resources, so the architect should propose m710p cartridges, which provide 10GbE ports. D)  The memory becomes a bottleneck before other resources, so the architect should propose m400 cartridges, which provide a higher memory capacity. Refer to the exhibit. An architect is planning an HPE Moonshot System with m710 cartridges to support a customer application virtualization solution. The customer indicated that the maximum acceptable response time for the solution is three seconds. The architect has implemented a POC and tested a single cartridge with different numbers of user sessions. The architect monitored resource utilization throughout the tests. The results of the test with the point at which the response time exceeded three seconds are shown, marked as the "VSI max." What should the architect conclude from this test?


A) CPU becomes a limiting factor around 50 sessions, so the architect should propose at least one cartridge per 45 or 50 users.
B) None of the monitored resources shows signs of being a bottleneck, so the architect should consider other factors such as the HPE Moonshot switch module.
C) The network adapter becomes a bottleneck before other resources, so the architect should propose m710p cartridges, which provide 10GbE ports.
D) The memory becomes a bottleneck before other resources, so the architect should propose m400 cartridges, which provide a higher memory capacity.

Correct Answer

verifed

verified

C

An architect proposes an HPE Moonshot server solution for a customer. The customer needs a single processor solution with a network switch to allow 10Gb connectivity and support for a software-defined network solution. Which HPE Moonshot switch module meets the customer's needs?


A) 180G Switch Module
B) 45Gc Switch Module
C) 45XGc Switch Module
D) 45G Switch Module

Correct Answer

verifed

verified

What is a basic assumption for an architect using the HPE Servers TCO calculator to justify a customer's migration away from a fully depreciated set of hardware?


A) By analyzing the project's internal rate of return (IRR) , it is possible to determine if the lower IRR will make it more desirable to undertake the project.
B) When the customer's older systems are under a support contract, a new system can sometimes pay for itself simply by not renewing the older support contracts.
C) The Net Present Value (NPV) is the difference between the value of the older systems and the cost of the new systems.
D) The opportunity costs of not migrating from a legacy environment to an HPE Converged Infrastructure Solution, in terms of IT Efficiency and User Productivity, will always justify the purchase.

Correct Answer

verifed

verified

During a data center transformation discussion, an architect obtains the following customer information: core business depends heavily on advanced data modelling techniques that has been developed internally infrastructure in use takes anywhere from 10 hours to five days to complete complex data models for the various development teams that rely on them has a proud reputation as an "environmentally friendly" Fortune 500 company increasing productivity of its development team is the highest priority Which large scale HPC solution should the architect recommend to help the customer achieve its transformation goals?


A) HPE Apollo 8000
B) HPE Integrity Superdome X
C) HPE Apollo 2000
D) HPE Apollo 6000

Correct Answer

verifed

verified

A customer plans to use Insight Control server provisioning and HPE OneView for vCenter Server. The vCenter Server manages one c7000 enclosure with 16 server blades running VMware ESXI. Which licensing option should the architect include in the proposal?


A) one HPE OneView Standard license for each managed server and one HPE OneView for vCenter Server license for the c7000 enclosure
B) one Insight Control server provisioning license for each managed server
C) one Insight Control server provisioning license for each managed server blade and one HPE OneView for vCenter Server license for the entire c7000 enclosure
D) one HPE OneView Advanced license for each managed server

Correct Answer

verifed

verified

An architect is proposing a solution that has two HPE Moonshot 1500 chassis, each of which is full of m700 cartridges. The customer needs the solution to quickly deploy the OS to cartridges, back up a golden node image. and clone the image. The customer is concerned about cost and is not interested in managing or monitoring performance of the solution, Which solution meets these requirements?


A) HPE Insight Cluster Management Utility (CMU)
B) HPE Intelligent Provisioning (IP)
C) HPE OneView 2.0
D) HPE Insight Control server provisioning (ICsp)

Correct Answer

verifed

verified

An architect needs to design a solution for a customer that stores all data on third-party NAS storage, and that does not yet have a database solution. The new HPE-based solution must be optimized for data mining. How can the current data stored on the NAS be used for data mining?


A) connecting the database to the NAS as main storage by using a TOE Host Bus Adapter
B) using the database application import functionality to migrate the data from the NAS to block-level storage for processing
C) attaching the database directly to the NAS storage by using a Fibre Channel Host Bus Adapter and by using the NAS for all DB tables
D) attaching the database directly to the NAS storage by using an iSCSI Host Bus Adapter and by using the NAS for all DB tables

Correct Answer

verifed

verified

A customer has a large Oracle-based ERP solution that runs on HPUX and multiple rx2800 i2 servers. The customer plans to move to an open source solution to reduce operating expenses. The customer needs the ability to deliver incremental capacity and needs to avoid incremental Oracle licensing costs. Which HPE Server solution will help meet the customer's needs?


A) HPE Apollo 6000 System
B) HPE Superdome X
C) HPE BladeSystem c7000 with BL460G Gen9 Servers
D) HPE Apollo 4500 System

Correct Answer

verifed

verified

An architect is designing an HPE Apollo 6000 solution to support an HPC application that is highly parallel and involves a lot of communication between compute nodes. The architect is choosing the FlexibleLOM options for the compute trays. Which technology should the architect ensure that the trays support?


A) VXLAN offloading
B) Fibre Channel over Ethernet (FCoE)
C) RDMA over Converged Ethernet (RoCE)
D) iSCSI hardware imitator

Correct Answer

verifed

verified

An architect reviews an HPE Apollo 6000 design and finds that there are plans for redundant iLO connections on each HPE Apollo 6000 chassis to a pair of top-of-rack switches. These switches are set up as individual switches connected to a single core. Which configuration change should the architect recommend to ensure a loop free management topology?


A) Remove one iLO connection from each HPE Apollo 6000 chassis.
B) Configure MAD between the top-of-rack switches.
C) Replace the top-of-rack switches with HPE Advanced Power Management Kits.
D) Configure IRF between the top-of-rack switches.

Correct Answer

verifed

verified

An architect proposes an HPE Moonshot 1500 chassis with m710p cartridges, an HPE Moonshot 45XGc Switch, and an HPE 4-QSFP+Uplink Module. The customer informs the architect that each cartridge requires a redundant 10GbE link. How should the architect change the proposal?


A) Add another FlexibleLOM adapter for each cartridge.
B) Change the HPE Moonshot 45XGc Switch to an HPE Moonshot 180G switch.
C) Add another HPE Moonshot 45XGc Switch and 4-QSFP+Uplink Module.
D) Change the 4-QSFP+Uplink Module to a 16-SFP+ Uplink Module.

Correct Answer

verifed

verified

A customer has an HPE Integrity Superdome X solution. The customer requires flexible nPartitions that IT staff can quickly build at different times based on a pre-defined template. Which approach should the architect recommend the customer take to meet this requirement?


A) Create nPartition configs using the iLO GUI for the HPE Integrity Superdome X blades.
B) Create nPartition build plans in HPE Insight Control server provisioning (ICsp) .
C) Create server templates in HPE OneView 2.0.
D) Create ParSpecs in the HPE Superdome Onboard Administrator (SD OA) .

Correct Answer

verifed

verified

An architect is planning an HPE Moonshot System deployment. The architect plans to individually connect each iLO CM module to the management network. The customer informs the architect that this plan requires too many 1GbE ports per rack for the data center infrastructure. What is one way that the architect can alter the plan to meet the customer's needs, while still allowing iLO access to the HPE Moonshot Systems?


A) Configure iLO traffic to share the same adapters as production traffic. Configure VLANs on the HPE Moonshot switch modules to separate the two types of traffic.
B) Keep one iLO CM Management port connected to the network. Use the iLO CM link ports on each iLO CM module to daisy chain the chassis together.
C) Enable the iLO REST API on each cartridge node. The nodes will then accept iLO commands on the adapters that they use for production traffic.
D) Add a second switch module and uplink module to each chassis to connect to the cartridge iLO ports. Stack the modules in different chassis and connect just one to the management network.

Correct Answer

verifed

verified

A customer is working on a project to enable workplace productivity. The customer needs a solution that will allow employees to connect to their workplace environment by using a personal mobile phone, tablet, laptop, or desktop computer. Employees must be able to stop and resume work seamlessly while travelling between offices. Which purpose-built hardware can the customer use to help achieve this goal?


A) HPE Moonshot to provide hosted physical desktop and application virtualization t mobile users
B) HPE Apollo 2000 to provide VDI access to mobile users
C) HPE Moonshot to provide VDI access to mobile users
D) HPE Apollo 2000 to provide hosted physical desktop and application virtualization to mobile users

Correct Answer

verifed

verified

A customer has a mixed environment based on the G6, G7, Gen8, and Gen9 ProLiant server blades. The customer is interested in implementing HPE OneView but needs to understand security and monitoring mechanisms for different server generations. Which statement most accurately describes different platform support in HPE OneView?


A) WBEM Providers will be used for any server managed by HPE OneView.
B) All servers managed by HPE OneView will use WBEM Providers, but collected data must be translated to the SNMP traps using embedded WMI Mapper.
C) HPE OneView can manage G7, Gen8/Gen9 servers, while G6 servers can only be monitored.
D) The customer can select from different management protocols between SNMP V2 and SNMP VS to match the security requirements.

Correct Answer

verifed

verified

A

A customer needs a hosted physical desktop solution. Users will run typical o?ice applications with limited use of some media-rich applications such as Adobe Photoshop. The customer needs the densest and most cost-effective solution that can support such users. Which HPE Moonshot cartridge should the architect recommend?


A) HPE m710
B) HPE m400
C) HPE m700
D) HPE m710p

Correct Answer

verifed

verified

D