The latest starting time for an activity is equal to the latest finish time minus the activity time.

Correct Answer

verifed

verified

Consider the portion of a project depicted by this graph: Consider the portion of a project depicted by this graph:   What is the earliest finish time for activity 10-11 (far right hand side) , if the earliest start time of 8-10 (upper left hand side)  is 12, and the earliest start time of 9-10 (lower left hand side)  is 13? A) 22 B) 23 C) 24 D) 25 E) 26 What is the earliest finish time for activity 10-11 (far right hand side) , if the earliest start time of 8-10 (upper left hand side) is 12, and the earliest start time of 9-10 (lower left hand side) is 13?


A) 22
B) 23
C) 24
D) 25
E) 26

Correct Answer

verifed

verified

At which point does crashing of a project cease?


A) when the project is completed
B) when no additional crashing is possible
C) when the cost to crash equals or exceeds the benefit of crashing
D) when the project is one-half completed
E) none of the above

Correct Answer

verifed

verified

Concerning PERT and CPM:


A) These are two different names for essentially the same technique.
B) CPM tends to focus more on the critical path; PERT focuses on the parallel paths.
C) PERT gives a clearer indication of activity slack, while CPM gives a better picture of path slack.
D) Because of its recent discovery, much less is known about CPM than PERT.
E) All of the above are true.

Correct Answer

verifed

verified

What are the estimated slack times (in weeks) for activities A-H?

Correct Answer

verifed

verified

0; 5; 15; ...

View Answer

What is the estimated slack time for Activity E?


A) 0 weeks
B) 3 weeks
C) 9 weeks
D) 11 weeks
E) 12 weeks

Correct Answer

verifed

verified

What is the estimated standard deviation in the time for activity E?


A) 1 days
B) 2 days
C) 3 days
D) 4 days
E) 5 days

Correct Answer

verifed

verified

The advantage(s) a precedence diagram has over a Gantt chart is(are) :


A) its ability to reveal relationships among activities.
B) it can easily show networks.
C) (a) and (b) .
D) its simplicity.
E) all of the above.

Correct Answer

verifed

verified

Activities not on the critical path have a slack time equal to zero.

Correct Answer

verifed

verified

In "crashing" a project, a manager will generally focus on activities which:


A) are not on the critical path
B) are the least costly to crash
C) are costly to crash and are on the critical path
D) are on the critical path and are the least costly to crash
E) are the easiest to crash

Correct Answer

verifed

verified

What are the estimated standard deviations (in weeks) in the times for activities A-H?

Correct Answer

verifed

verified

2; 1.67; 2...

View Answer

What is the estimated expected (mean) time for activity E?


A) 35 days
B) 36 days
C) 39 days
D) 40 days
E) 45 days

Correct Answer

verifed

verified

A node has one entering activity, a, and two leaving activities, b and c.Given the following information, determine the latest starting time for activity a: EFb = 15, EFc = 17, LFb = 24, LFc = 27; activity times are a = 4, b = 6, c = 8.


A) 14
B) 15
C) 16
D) 17
E) 18

Correct Answer

verifed

verified

The earliest finish time for an activity is equal to the latest finish time minus the activity time.

Correct Answer

verifed

verified

Which of the following would probably not involve the use of PERT?


A) planning and constructing a new city hall
B) developing an advertising campaign for a new product
C) designing and constructing a subway system
D) writing a poem
E) preparing for the visit of a foreign dignitary

Correct Answer

verifed

verified

What is the estimated standard deviation in the time for activity Z?


A) 3 days
B) 2 days
C) 4 days
D) 8 days
E) 5 days

Correct Answer

verifed

verified

When developing probabilistic estimates of project duration, it is necessary to know which of the following?


A) the mean and variance of every activity
B) the mean and variance of activities on the critical path
C) the standard deviation of activities on the critical path
D) each activity's probability of completion
E) the distribution of activity times

Correct Answer

verifed

verified

Which of the following is not a form of risk reduction in project management?


A) backup system
B) outsourcing
C) risk-sharing
D) scenario analysis
E) all of the above are risk reduction methods

Correct Answer

verifed

verified

The path in a network with the average length of time to completion is called the critical path.

Correct Answer

verifed

verified

A project consists of nine major activities, as shown below.There are three separate paths in the network: a-c-f, b-d-g, and e-h-i. (A) What is expected project duration time? (B) Determine the probability that the project will take more than 35 weeks to complete.(All times are in weeks.)

Correct Answer

verifed

verified

blured image blured image blured image A) Expected duration = 32 w...

View Answer

Showing 61 - 80 of 137