Filters
Question type

Study Flashcards

If your project has spent $50,000 versus a budget of $45,000 and it is a week ahead of schedule, is it a certainty that your project is doing well?

Correct Answer

verifed

verified

Not necessarily.You ...

View Answer

Scheduling time-constrained projects focuses on resource utilization.

Correct Answer

verifed

verified

Regina's boss has told her that her project is very important.If the critical path is delayed, she will be given whatever she needs to get it back on schedule.Her project is ________ constrained.


A) Time
B) Quality
C) Cost
D) Performance
E) Resource

Correct Answer

verifed

verified

Which of the following is a potential consequence of failing to schedule limited resources?


A) Costly activity delays
B) Costly project delays
C) Difficulty in taking quick corrective action
D) Both A and B are correct
E) A, B, and C are all correct

Correct Answer

verifed

verified

Many companies are using ________ from contractors and consultants as a means of dealing with the peaks and valleys of resource allocation among projects.

Correct Answer

verifed

verified

outsourcing
Explanation: Many companies ...

View Answer

If resources are not adequate to meet peak demands, the resulting reschedule is termed


A) Resource-constrained scheduling
B) Time-constrained scheduling
C) Mandatory leveling
D) Project resource adjustment
E) Allocation

Correct Answer

verifed

verified

Which of the following is not one of the more common problems associated with scheduling multiproject resources?


A) Overall schedule slippage
B) Inefficient resource utilization
C) Resource bottlenecks
D) Both A and C are correct
E) A, B, and C are all correct

Correct Answer

verifed

verified

Delaying noncritical activities to lower peak demand on resources is known as resource


A) Shifting
B) Effectiveness
C) Manipulating
D) Resource smoothing
E) Allocation

Correct Answer

verifed

verified

The word Heuristics means


A) Resource constraints
B) Flexibility
C) The critical path changed
D) Parallel activities become sequential
E) Rule of thumb

Correct Answer

verifed

verified

Beth has two engineers assigned to her project and cannot get any more even if it means slipping the due date on her project.She is managing a(n) ________ constrained project.

Correct Answer

verifed

verified

resource
Explanation: A resource-constra...

View Answer

The critical path in a resource-constrained schedule can be a group of disjointed, unconnected activities.

Correct Answer

verifed

verified

When using the ________ scheduling technique, the work in an activity is interrupted to work on another activity and is then resumed at a later point in time.

Correct Answer

verifed

verified

splitting or multitasking
Explanation: A...

View Answer

Why should project managers be cautious about using the splitting scheduling technique?

Correct Answer

verifed

verified

The splitting technique is where an acti...

View Answer

Resource leveling can provide


A) Lower peak demand
B) Reduced resource need over the life of the project
C) Reduced fluctuations in resource demand
D) Both A and B are correct
E) A, B, and C are all correct

Correct Answer

verifed

verified

Splitting is a scheduling technique used to get a better schedule or better resource utilization.

Correct Answer

verifed

verified

Heuristics are used in resource-constrained projects to develop the optimal schedule.

Correct Answer

verifed

verified

The ________ is the most widely used approach to apply heuristic rules to scheduling activities in a constrained project.

Correct Answer

verifed

verified

parallel method
Explanation: T...

View Answer

The most obvious and important kind of resource constraint is a lack of materials.

Correct Answer

verifed

verified

To determine if a project is time-constrained or resource-constrained you would consult the project priority matrix.

Correct Answer

verifed

verified

Too many parallel activities for one individual are an example of a resource constraint.

Correct Answer

verifed

verified

Showing 61 - 80 of 90

Related Exams

Show Answer