Sean is forecasting the time and cost of developing a customized software program by looking at the number of inputs,outputs,inquiries,files,and interfaces.Which of the following methods is he using?


A) Ratio
B) Template
C) Apportion
D) Function point
E) Learning curve

Correct Answer

verifed

verified

Refining estimates may be necessary for a number of reasons.For example,design flaws being revealed after the fact,extreme weather conditions,and accidents occurring are good examples of


A) Hidden interaction costs.
B) Things going wrong on a project.
C) Normal conditions not applying.
D) Changes in project scope.
E) None of these are correct.

Correct Answer

verifed

verified

Ed is looking over the actual results of projects and comparing them to what was estimated.He notices that the projects that took six months or longer to complete were noticeably more off the estimates.Which of the following factors is he recognizing?


A) Padding estimates
B) Project duration
C) Project structure
D) People
E) Organization culture

Correct Answer

verifed

verified

After averaging out the underestimates and overestimates,a long-duration project is more likely to be on target than a short-term,small project.

Correct Answer

verifed

verified

The consensus method of estimating costs is a bottom-up technique.

Correct Answer

verifed

verified

The estimating factor that considers the decreasing accuracy of estimates as one forecasts activities that are further into the future is known as ____________.

Correct Answer

verifed

verified

planning horizon
Explanation: The qualit...

View Answer

Costs that are associated with time devoted to the coordination in meetings and briefings as well as time necessary to resolve disconnects between tasks are known as ____________ costs.

Correct Answer

verifed

verified

interaction
Explanation: Time,...

View Answer

The bottom-up method of estimating where work package time and costs for past projects are used as a starting point for a new project and adjustments are made based on differences in the new project is known as the ___________ method.

Correct Answer

verifed

verified

template
Explanation: If the project is ...

View Answer

Phase estimating is used when a project cannot be rigorously defined because of the uncertainty of design or the final product.

Correct Answer

verifed

verified

Which of the following is NOT true in regard to the level of detail estimates should contain?


A) It will vary with the complexity of the project
B) Detailed estimates are crucial to project success;therefore,an effort should be made to make estimates as detailed as possible for all projects
C) The more detailed the estimate is the more the estimate will cost to create
D) Inadequate detail might lead to estimates that fall short of their intended purpose
E) Excessive detail means unproductive paperwork and unnecessary expenditures

Correct Answer

verifed

verified

The preferred method for situations involving strategic decision making,projects with a high degree of uncertainty,and projects with an unstable scope is the ___________ approach to estimating project time and costs.

Correct Answer

verifed

verified

top-down
Explanation: Good conditions fo...

View Answer

When work package estimates are made by individuals most knowledgeable about the work being performed and these estimates are then "rolled up" to find estimated costs for major deliverables and the project itself,____________ estimating is being used.

Correct Answer

verifed

verified

bottom-up
Explanation: The bottom-up app...

View Answer

The estimating factor that considers the tendency to overestimate project time and cost in order to improve the likelihood of meeting the estimates is known as the ___________ factor.

Correct Answer

verifed

verified

padding estimates
Explanation: In work s...

View Answer

Which of the following is NOT one of the factors that need to be considered to improve quality of estimates for project times and costs?


A) Planning horizon
B) People
C) Padding estimates
D) Profit
E) Project structure

Correct Answer

verifed

verified

Past experience is almost always used primarily in the initial phases of estimating.

Correct Answer

verifed

verified

Cost,time,and budget estimates are the lifeline for control;they serve as the standard for comparison of the actual and the planned throughout the life of the project.

Correct Answer

verifed

verified

Jose is forecasting project time and cost for constructing a new building by multiplying the total square footage by a given dollar amount.He is using the ___________ method of top-down estimating.

Correct Answer

verifed

verified

ratio
Explanation: Top-down methods (som...

View Answer

If a project is internal to the company and relatively small,the bottom-up approach to estimating time and costs for the project is the best choice.

Correct Answer

verifed

verified

A good starting point for developing time and cost estimates is


A) Past experience.
B) Work packages.
C) Task analysis.
D) Time and motion studies.
E) Work breakdown structure.

Correct Answer

verifed

verified

Laura is forecasting the time and cost of developing an intranet for a new customer.Her department has completed six such intranets for customers during the last two years.Although the proposed system is about the same size as the others,she estimates that it will take about 10 percent less time and money.Which of the following methods is she using?


A) Ratio
B) Template
C) Apportion
D) Function point
E) Learning curve

Correct Answer

verifed

verified