The first step in creating a project control system for measuring and evaluating project performance is to set a ________.

Correct Answer

verifed

verified

baseline plan
Explanation: The project c...

View Answer

Which performance index is the most potentially misleading?


A) CPI
B) EV
C) CV
D) SV
E) EAC

Correct Answer

verifed

verified

When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the


A) 0/100 percent rule.
B) Task complete rule.
C) Degree complete rule.
D) Work complete rule.
E) Percent complete rule.

Correct Answer

verifed

verified

The value that tells you the planned value of the actual work completed is ___________.

Correct Answer

verifed

verified

earned value
Explanation: Earn...

View Answer

The Schedule Variance is the best way to get an accurate assessment of schedule performance.

Correct Answer

verifed

verified

A project can have a negative Schedule Variance and still be ahead of schedule when A.All budget targets have been achieved. B.Non-Critical task delays are greater than progress on the Critical Path. C.Progress on the Critical Path is faster than non-critical path tasks. D.None of these choices are correct.

Correct Answer

verifed

verified

A.All budget targets have been achieved....

View Answer

Although it is very difficult to measure, measuring technical performance is as important as measuring schedule and cost performance.

Correct Answer

verifed

verified

Two project complete indexes are used, depending on your judgment of which one is most representative of your project.Identify both indexes and explain when it is most appropriate to use each.

Correct Answer

verifed

verified

The PCIB assumes the original budget of ...

View Answer

A negative Cost Variance combined with a negative Schedule Variance is an indicator of


A) Actual Cost running to plan.
B) Risk of Work Packages running out of Slack.
C) Budget over-runs.
D) None of these choices are correct.

Correct Answer

verifed

verified

Which of the following methods will measure the cost efficiency of the work accomplished to date?


A) SV/CV
B) EV/PV
C) EV/AC
D) AC/SV
E) AC/CV

Correct Answer

verifed

verified

A project monitoring system involves all of the following EXCEPT


A) Determining what data to collect.
B) Determining how, when, and who will collect the data.
C) Adjusting the data.
D) Analysis of the data.
E) Reporting current progress.

Correct Answer

verifed

verified

The second step in the project control process for measuring and evaluating project performance is to


A) Review the baseline plan with top management.
B) Analyze inputs to control system.
C) Compare plan against actual.
D) Measure progress and performance.
E) Review spending with team members.

Correct Answer

verifed

verified

A ___________ Gantt chart is a simple and effective way to depict progress on a project.


A) Baseline
B) Control
C) Variance
D) Tracking
E) Simple

Correct Answer

verifed

verified

Which of the following methods will measure the scheduling efficiency of the work accomplished to date?


A) SV/CV
B) EV/PV
C) EV/AC
D) AC/SV
E) AC/CV

Correct Answer

verifed

verified

Conducting an earned value analysis requires three data elements.Identify the acronyms for each and describe what they are.

Correct Answer

verifed

verified

(1)PV-budgeted cost of work sc...

View Answer

Because of their easy-to-understand visual format, ________ charts are the most favored, used, and understandable tool used to report project schedule status.

Correct Answer

verifed

verified

Gantt
Explanation: Gantt and control cha...

View Answer

The PV, AC and CV are all required to assess the current status of the project.

Correct Answer

verifed

verified

A scope change is always viewed negatively as it changes the delivery date of the project.

Correct Answer

verifed

verified

What is the difference between a baseline Gantt chart and a tracking Gantt chart?

Correct Answer

verifed

verified

The baseline chart is created during the...

View Answer

When reviewing the variance on a project, you compare Earned Value with


A) Actual Costs.
B) Realized Risks.
C) Expected Schedule Value.
D) Actual Costs and Expected Schedule Value.

Correct Answer

verifed

verified