In the network computation process what is a backward pass and what four things does it determine?

Correct Answer

verifed

verified

Starting with the last activity, each pa...

View Answer

The ________ calculates the critical path and determines how long an activity can be delayed without delaying the project.

Correct Answer

verifed

verified

backward pass
Explanation: The backward ...

View Answer

Only activities that occur at the end of a chain of activities can have free slack.

Correct Answer

verifed

verified

If the project has a duration of 13 days, the project should be completed 13 days from the day it starts.

Correct Answer

verifed

verified

If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?


A) Check to see which activities cost the least.
B) Check to see which activities have the longest duration.
C) Check to see which activities are on the critical path.
D) Check to see which activities have the most slack.
E) Check to see which activities have the highest risk.

Correct Answer

verifed

verified

What is a Gantt chart and what advantages does it have over project networks?

Correct Answer

verifed

verified

Gantt charts are bar charts where activi...

View Answer

System documentation cannot end until three days after testing has started.This is an example of which kind of lag?


A) Start to Start
B) Start to Finish
C) Finish to Finish
D) Finish to Start
E) Any of these could be correct.

Correct Answer

verifed

verified

Which of the following is NOT one of the basic rules to follow when developing project networks?


A) An activity cannot begin until all preceding activities have been completed.
B) Each activity must have a unique identification number.
C) Conditional statements are allowed but looping statements are not allowed.
D) An activity identification number must be larger than that of any preceding activities.
E) Networks flow from left to right.

Correct Answer

verifed

verified

On a project network, the activity times are derived from the


A) Organization breakdown structure.
B) Work packages.
C) Budget.
D) Project proposal.
E) Responsibility matrix.

Correct Answer

verifed

verified

________ can never be negative and applies only to the last activity in a single chain of activities.

Correct Answer

verifed

verified

Free slack
Explanation: Free slack is th...

View Answer

The ________ calculates the earliest times that activities can start or finish.

Correct Answer

verifed

verified

forward pass
Explanation: The ...

View Answer

One piece of information that the arrows within the Activity-on-Node network can convey is


A) the duration of an activity.
B) the amount of risk inherent in an activity.
C) how activities are related.
D) None of these choices are correct.

Correct Answer

verifed

verified

It is possible for a project network to have more than one critical path.

Correct Answer

verifed

verified

In the network computation process what is a forward pass and what three things does it determine?

Correct Answer

verifed

verified

Starting with the first activity, each p...

View Answer

The requirement for a freshly poured foundation to cure before beginning construction is an example of which of the following type of lag?


A) Start to Start
B) Start to Finish
C) Finish to Finish
D) Finish to Start
E) Any of these could be correct.

Correct Answer

verifed

verified

A(n)________ is the minimum amount of time a dependent activity must be delayed to begin or end.

Correct Answer

verifed

verified

lag
Explanation: A lag is the ...

View Answer

Identify and briefly describe the four types of lags giving an example for each type.

Correct Answer

verifed

verified

(1)Finish-to-Start.
...

View Answer

Which of the following will correctly calculate the total slack in an activity?


A) LS - ES
B) LF - EF
C) LS - LF
D) LF - ES
E) Either LS - ES or LF - EF

Correct Answer

verifed

verified

An activity cannot begin until ALL preceding connected activities have been completed.

Correct Answer

verifed

verified

Negative slack can be estimated.

Correct Answer

verifed

verified