Which of the following information about activities is not needed in determining how to crash a project?


A) the normal cost
B) the crash cost
C) the crash time estimate
D) the normal time estimate
E) how many dummy activities there are

Correct Answer

verifed

verified

Consider a project having the following ten activities: Normal Normal Crash Crash Maximum Immediate Time Cost Time Cost Weeks Activity Predecessors (weeks) ($) (weeks) ($) Reduced A none 7 3,000 6 6,000 1 B A 8 5,000 6 9,000 2 C A 2 2,000 1 3,000 1 D A 4 3,000 4 3,000 0 E B, C 9 4,000 7 6,000 2 F C, D 6 4,000 4 9,000 2 G E 2 3,000 2 3,000 0 H E, F 9 4,000 7 7,000 2 I G 1 4,000 1 4,000 0 J H, I 8 2,000 6 7,000 2 (a)What is the expected project completion time? (b)What is the critical path? (c)What is the most economical way and how much will it cost to reduce the completion time of the project by three weeks? by five weeks?

Correct Answer

verifed

verified

(a)41 weeks; (b)A-B-E-H-J; (c)three week...

View Answer

The process of calculating ES and EF ______________________________.


A) requires only a forward pass through the network
B) requires only a backward pass through the network
C) requires both a forward and backward pass through the network
D) cannot be accomplished until slack is first determined
E) is sufficient for calculating the critical path

Correct Answer

verifed

verified

Which of the following is not characteristic of a project?


A) has a life cycle
B) uses no resources
C) involves a unique, one-time event
D) consists of several tasks
E) typically some activities may be done simultaneously

Correct Answer

verifed

verified

The most likely time completion date is the _______________ of the beta distribution.

Correct Answer

verifed

verified

Which phase in the project life cycle involves analyzing the project risk?


A) conception
B) feasibility analysis or study
C) planning
D) execution
E) termination

Correct Answer

verifed

verified

Which of the following can be calculated for an activity once ES, EF, LS, and LF have been calculated for the activity?


A) expected project duration
B) slack time
C) potential for crashing
D) variance in project duration
E) the relative time position for when the activity will be completed

Correct Answer

verifed

verified

Critical path shows the _______________ completion time for the project.

Correct Answer

verifed

verified

We use _____________________ time estimates when we can make a reliable estimate.


A) variable
B) probabilistic
C) estimated
D) deterministic
E) cumulative

Correct Answer

verifed

verified

What is a unique, one-time event that is intended to achieve an objective in a given time period?


A) a project
B) a job
C) a task
D) an activity
E) an event

Correct Answer

verifed

verified

Consider a project having the following seven activities: Normal Normal Crash Crash Maximum Immediate Time Cost Time Cost Weeks Activity Predecessors (weeks) ($) (weeks) ($) Reduced A none 4 3,000 3 5,000 1 B A 9 5,000 7 8,000 2 C A 4 7,000 4 7,000 0 D B, C 6 6,000 4 8,000 2 E C 8 4,000 6 8,000 2 F D 3 4,000 2 9,000 1 G E, F 4 2,000 2 7,000 2 (a)What is the expected project completion time? (b)What is the critical path? (c)What is the most economical way and how much will it cost to reduce the completion time of the project by three weeks? By five weeks?

Correct Answer

verifed

verified

(a)26 weeks; (b)A-B-D-F-G; (c)three week...

View Answer

Define crashing as it relates to project management.

Correct Answer

verifed

verified

Crashing is reducing...

View Answer

What is involved in the approach for crashing projects?

Correct Answer

verifed

verified

Determine how much the project needs to ...

View Answer

Given this information about an activity: ES = 10, EF = 20, LS = 29, and LF = 39. The amount of slack associated with the activity is ____________________.


A) 29
B) 9
C) 19
D) 38
E) 10

Correct Answer

verifed

verified

Which of the following is not included in the approach for crashing projects?


A) Determine which activity requires the most time.
B) Crash the least expensive activity first.
C) Determine how much the project needs to be reduced.
D) Calculate the total costs associated with crashing the project.
E) Determine which activities on the critical path can be reduced.

Correct Answer

verifed

verified

With probabilistic time estimates for activities, (o) denotes the _______________________.


A) median time
B) original time
C) optimistic time
D) pessimistic time
E) most likely time

Correct Answer

verifed

verified

There are four activities on the critical path, and they have variances of 1, 2, 4, and 2. The variance of the critical path is _______.


A) 3
B) 5
C) 9
D) 16
E) 25

Correct Answer

verifed

verified

In the TOC, if delays exceed the feeding buffer, the project completion date is still protected by the ____________.

Correct Answer

verifed

verified

Name and describe the three ways to waste safety time in the critical chain approach.

Correct Answer

verifed

verified

the student approach, which involves del...

View Answer

Consider a project having the following seven activities: Immediate Activity Predecessors Time (weeks) A none 4 B none 6 C A 9 D A 7 E B 4 F D, E 5 G F 4 (a)What is the critical time? (b)What is the critical path? (c)What is the slack for each activity?

Correct Answer

verifed

verified

(a)20 weeks; (b)A-D-F-G; (c)A ...