A) Modify the cost on arc 4-5 to account for only operating costs.
B) Add a second arc 4-5 to represent just the operating costs.
C) Add a dummy node, 6, so that arc 4-6 represents just the operating costs.
D) Add a dummy node, 6, so that arc 4-5 represents operating costs and 5-6 represents new equipment purchase.
Correct Answer
verified
Multiple Choice
A) positive numbers.
B) negative numbers.
C) imaginary numbers.
D) either positive or negative numbers.
Correct Answer
verified
Multiple Choice
A) transportation problem.
B) shortest path problem.
C) maximal flow problem.
D) minimal spanning tree problem.
Correct Answer
verified
Essay
Correct Answer
verified
Multiple Choice
A) linear programming
B) network flow methods
C) trial and error
D) simulation
Correct Answer
verified
Multiple Choice
A) SUMIF($C$6:$C$16,I6,$B$6:$B$16) −SUMIF($E$6:$E$16,I6,$B$6:$B$16)
B) SUMIF($I$6:$I$12,B6,$B$6:$B$16) −SUMIF($I$6:$I$12,I6,$B$6:$B$16)
C) SUMIF($E$6:$E$16,I6,$B$6:$B$16) −SUMIF($C$6:$C$16,I6,$B$6:$B$16)
D) SUMPRODUCT(B6:B16,G6:G16)
Correct Answer
verified
Multiple Choice
A) The model solution is not guaranteed to be integer.
B) The model solution will more accurately reflect reality.
C) The model solution will be integer but more accurate.
D) The model solution is not guaranteed to be feasible.
Correct Answer
verified
Multiple Choice
A) X12 + X23 = 100
B) X12 − X23 ≤ 100
C) −X12 + X23 ≥ −100
D) X12 − X23 ≥ 100
Correct Answer
verified
Essay
Correct Answer
verified
Multiple Choice
A) add extra supply arcs
B) remove the extra demand arcs
C) add a dummy supply
D) add a dummy demand
Correct Answer
verified
Multiple Choice
A) connecting the supply and demand nodes with a return arc
B) adding extra supply nodes
C) adding supply limits on the supply nodes
D) requiring integer solutions
Correct Answer
verified
Multiple Choice
A) demand
B) supply
C) random
D) decision
Correct Answer
verified
Multiple Choice
A) X13 + X23 − .95 X35 − .90 X36 − .90 X37 = 0
B) .80 X13 + .95 X23 − X35 − X36 − X37 = 0
C) .80 X13 + .95 X23 − .90 X36 − .90 X37 ≥ 0
D) X13 + X23 − X35 − X36 − X37 ≥ 0
Correct Answer
verified
Multiple Choice
A) the sums of all rows and columns equal to one.
B) binary decision variables.
C) non-negativity constraints removed.
D) all of the above.
Correct Answer
verified
Multiple Choice
A) Inflow − Outflow ≤ Supply or Demand
B) Inflow − Outflow ≥ Supply or Demand
C) Inflow − Outflow = Supply or Demand
D) Inflow − Supply ≥ Outflow or Demand
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) nodes.
B) arcs.
C) demands.
D) supplies.
Correct Answer
verified
Multiple Choice
A) Place a limit of 34 on each in-flow arc.
B) Add a side constraint limiting the out-flow arcs sum to 100.
C) Separate the warehouse node into two nodes, connected by a single arc, with capacity of 100.
D) It cannot be accomplished, a side constraint must be added.
Correct Answer
verified
Essay
Correct Answer
verified
Multiple Choice
A) have total demanded quantities expressed as positive numbers
B) have all directed arcs originating at them
C) have some unidirectional arcs
D) have total available quantities expressed as negative numbers
Correct Answer
verified
Showing 41 - 60 of 92
Related Exams